Contract Audit

Contract management is the core of everything EQP does. It’s where we developed our proprietary methodology and built the technical depth that underpins our entire portfolio.

Over nearly 20 years, we have structured, audited, and optimized contracts in complex operations, translating contract management into financial and operational results.

What challenges do companies face in the market?

Contract owners often manage contracts without full technical command, relying on informal practices and little evidence based verification: measurements approved without validation, outdated documentation, and poor visibility into what’s actually being executed.

Without a structured analysis:

When the problem shows up:

What is a Contract Audit?

It is an independent verification that compares three dimensions:

EQP does not perform only document analysis.
Verification is carried out on site, validating whether the operation truly adheres to what was contracted.

The result is a complete diagnosis with:

Important: It is not optimization. It’s not renegotiation. It is a diagnosis of compliance and compliance.

What are the benefits of Contract Audit?

Compliance and Risk

Financial

Governance

Supplier Management

What results have we already delivered with Contract Audit?

Segment
Contract scope
Identified situation
Result achieved
Mining
Magnet maintenance (vibrating screen)
Take or pay contract with recurring stoppages and low adherence to actual use. Cleaning clause not executed due to lack of infrastructure and lack of awareness by the contract owner.
Production impact
US$ 3 million/year
Mining
Ore transport and handling
Execution outside the contract scope, informal agreements, SLA failures, and lack of systematic validation of measurements.
Identified divergences
R$ 1.1 to 1.9 million in a single contract
Mining
Off road tire repairs
Active operation without a current contract, with people and assets without contractual coverage or insurance.
Critical risk
Recommendation for immediate demobilization
Agribusiness
Employee meals
Third party workers used the cafeteria at the client’s expense, even though meal costs were already included in the fees paid to the contractors.
Undue payments eliminated
R$ 160 thousand/year
Agribusiness
Bagasse supply
Measurements were approved without accounting for contractual stoppages. The review relied on gross hour meter readings and lacked technical control by the contract inspector.
Savings per equipment
R$ 80 thousand/year, with scale potential